Please visit here to see updates on the Baltimore Street Revitalization project!
Construction is moving along. Workers have placed the first layers of what will eventually be a brick road on Baltimore Street.
Planters have been placed among Baltimore Street! The planters were chosen with a rustic, modern feel. Giving a nod to our historic past while embracing the future. Once construction is done, flowers and shrubbery will be placed in the planters.
Progress is being made downtown! *Bricks are moving up Baltimore St. *Wind shade frames have been installed in CBIZ parklet *Light poles expected to arrive mid September
*Pavers are being installed in multiple areas throughout the project, and this will continue to be the main construction activity for the next few weeks. Centre Street will soon have all driving and parking area pavers installed. Please note that this street will remain closed until all sidewalk pavers and other construction items are completed […]
* Concrete work (curbs, road base, tree planters) is nearing completion. After this week, the only concrete work remaining will be at the intersection of Baltimore Street and Liberty Street. This intersection will be completed once the contractor for Verizon has finished modifying their concrete vault lid in this location. * Approximately half of the […]
This week, some London Plane trees were planted on Baltimore Street between Mechanic Street and Liberty Street. Additionally, all concrete work is completed on Centre Street and roadway pavers are being installed on North Centre Street. Concrete curbing and trench drains are starting to be installed on the last block of Baltimore Street between Centre […]
All silva cells for the project have been installed All underground water and sewer line work is complete (electric and 5G fiber is all that is left) Parking area pavers have been installed on North Liberty Street Street pavers are being installed on South Liberty Street
Week of February 26, 2024: Silva Cells were completed on the south side of Baltimore Street between Centre St and George St. Parking area pavers were installed on North Liberty Street. Concrete curbing was installed on Baltimore Street between Liberty St and Centre St. Electric and fiber lines installed on North Centre Street. Nearing completion. […]
The Baltimore Street Access construction project is on schedule and making progress! Recent updates include: * The Liberty Street demolition should be complete by early January. * Sewer and electric lines are done on Liberty Street. * 5G fiber has been extended from just Baltimore Street to include Liberty Street and Centre Street due to […]
In addition to the continued infrastructure work on Baltimore Street, highlights of the past month include: Placement of the Portland Loo public restroom in the Mechanic Street Welcome Plaza. Beginning the Silva Cell installation - The Silva Cell supports large tree growth and provides powerful on-site stormwater management through absorption, evapotranspiration, and interception. Installation of […]
In the last 2 weeks, Triton has installed utilities into the buildings in the western block of Baltimore Street, including new water service lines, fire suppression lines, fiber conduits, and sanitary sewer service lines. They have also installed new fire hydrants and yard hydrants in that area. The street now sits about a foot lower […]
The utility and infrastructure work continues on Baltimore Street and has moved into the intersection with Centre Street.
Work continues on the sewer and water lines on Baltimore Street between Mechanic Street and Liberty Street. The new water lines are now connected to the existing lines at Mechanic Street. The electrical sub-contractor has started at the Mechanic Street Plaza by CBIZ and will continue to work up Baltimore Street.
Safety barricades have been placed on Baltimore Street to separate the sidewalks and the construction zone.
The construction of the new Baltimore Street Project has been focused on the area between Mechanic Street and Liberty Street the past two weeks. The planters have been removed, as well as, the parklet by CBIZ. The McCoury Stage was removed this morning. The center of the mall has been blocked off with construction barrels […]
Trees will be removed on Liberty and Centre Streets beginning on Thursday, April 5th. The streets should not be completed blocked, but flaggers will be present to help traffic get through. You should expect some noise from the wood chipper and chain saws. Thanks for your patience!
Starting the week of April 3, Triton Construction will begin barricading the center of the pedestrian mall from Mechanic Street to Centre Street. You should also see the start of the removal of the concrete planters in the center of Baltimore Street and the addition of signage. Light poles on Baltimore Street from Mechanic Street […]
Groundbreaking for Baltimore Street Project Held on March 17, 2023
Please join us for the Baltimore Street Revitalization Project Groundbreaking Friday, March 17, 2023 at 12:30pm at the McCoury Stage, Baltimore and Liberty Streets!